Investments

01 January 2017

Erection of the first Top Recovery Turbine Installation in Poland

Erection of the first Top Recovery Turbine Installation using energy generated as a result of the expansion of blast furnace gas to generate electricity for ArcelorMittal Poland Unit in Dąbrowa Górnicza will soon be launched in Generation Plant Nowa.

In December 2016 following the completion of the pre-investment stage, TAMEH POLSKA sp. z o.o. concluded a contract for the general contracting of a turn-key investment with a Consortium composed of Primetals Technologies Austria GmbH and Przedsiębiorstwo Produkcyjno-Usługowo-Handlowe EKO-ENERGIA Sp. z o.o. The investment is to be completed at the end of 2018.