Modernization of a system supplying electric energy and compressed air of company ALKAT in Generation Plant Nowa completed

Modernization of the system supplying electric energy and compressed air of company ALKAT in Generation Plant Nowa was completed.

The project included 3 streams:

Stream 1 – Erection of a new power supply line:

  • Modernization of field 33 in GSE-11
  • New 1.5-kilometer 6kV cable line
  • New switching station 6kV S119 to supply 8MW air compressor of the new oxygen block of company ALKAT sp. z o.o.
  • Replacement of switching station 0,4kV T119

Stream 2 – Modernization of electrical infrastructure:

  • Modernization of switching station 6kV S103
  • Replacement of 3 cable lines 6kV
  • Replacement of switching station 0.4kV T103

Stream 3 – Erection of a compressed air installation:

  • Construction of collector C to supply compressed air from turbo compressors in Generation Plant Nowa to the new oxygen block of company ALKAT sp. z o.o.