Investments

January 2017

Modernization of a system supplying electric energy and compressed air of company ALKAT in Generation Plant Nowa completed

Modernization of the system supplying electric energy and compressed air of company ALKAT in Generation Plant Nowa was completed.

The project included 3 streams:

Stream 1 – Erection of a new power supply line:

  • Modernization of field 33 in GSE-11
  • New 1.5-kilometer 6kV cable line
  • New switching station 6kV S119 to supply 8MW air compressor of the new oxygen block of company ALKAT sp. z o.o.
  • Replacement of switching station 0,4kV T119

Stream 2 – Modernization of electrical infrastructure:

  • Modernization of switching station 6kV S103
  • Replacement of 3 cable lines 6kV
  • Replacement of switching station 0.4kV T103

Stream 3 – Erection of a compressed air installation:

  • Construction of collector C to supply compressed air from turbo compressors in Generation Plant Nowa to the new oxygen block of company ALKAT sp. z o.o.

As part of our site, we use cookies to provide you with the highest level of service, including in a manner tailored to individual needs. Using the site without changing the settings for cookies means that they will be placed on your device. You can change your cookie settings at any time. Find out more about our privacy policy.