01 August 2018

Halfway through the construction of a new turbo generator in Generation Plant Kraków

The erection of a new steam turbo set of the nominal power of 55MWe reached half point in August 2018. Foundation works are now in progress. A condenser weighing over 70 tons was delivered; its transport through the engine room proved to be a challenge but the entire operation was completed successfully.

The construction is planned to be completed in July 2019.